Chichester cut roof: made-to-measure design and build.

A difficult timber roof formed around blockwork that was not square, delayed lintels and incomplete drawings, using verified site dimensions and revised working details.

This Chichester roof could not be treated as a standard set-out exercise. The blockwork varied from the expected geometry, lintel delays interrupted the sequence and the available drawings did not fully resolve every roof junction.

Real site conditions changed the starting point

The blockwork was not square, so dimensions taken from an ideal drawing could not simply be transferred to the building. The roof also depended on lintels that held up progress, while incomplete drawings left important practical details to be resolved. Ridge lines, rafter lengths, bearing points and the relationship with the existing roof all had to be checked together.

A detailed, made-to-measure design-and-build process

Sixes Carpentry measured the constructed walls and existing roof, revised the working drawings to suit the verified dimensions and set out the timber package from those real conditions. Each section was coordinated so that corrections were absorbed deliberately rather than carried through the frame. The practical carpentry solution remained within the agreed project scope; any structural design changes and approvals remained the responsibility of the relevant appointed professionals.

Cut roof: before, during and frame complete

Initial cut-roof framing over blockwork during a Chichester roof project
Before — initial sectionThe first gable and rafter geometry exposed the relationship between the constructed walls and the required roof form.
Made-to-measure rafters and roof junctions during cut-roof carpentry in Chichester
During — coordinated framingRafters, hips and junctions were progressed using the revised working details and verified site dimensions.
Cut-roof timber framing complete over an extension in Chichester
After — frame completeThe made-to-measure timber structure completed across the extension, ready for the following roof stages.

The result

The completed cut roof turned incomplete information and imperfect masonry into a coordinated timber structure. The revised working drawings created a record of the measured solution, while careful setting-out allowed the carpentry to overcome the blockwork and programme issues encountered on site.

“What a great job they done! The team was so helpful and overcame issues we didnt even expect!”

Chichester customer

Project location: Chichester, West Sussex. Photographs show Sixes Carpentry's cut-roof work through to structural framing completion. Anonymous customer testimonial published with permission.

Call nowGet a quote